Sprint 2

· 2 min read

From: 2024-03-05

To: 2024-03-12

Scrum Master: André Oliveira

Product Owner: Alexandre Cotorobai

Developers: Joaquim Rosa, Duarte Cruz, Hugo Correia, Bernardo Figueiredo

Sprint Goal

In this sprint, we aimed to finish all the tags that were not possible to complete in the previous sprint and some that emerged at the last minute:

  • UI Mockups
  • Update all the documentation
  • LateX Report Repo Creation
  • Presentation Preparation
  • Use Cases Preparation
ExpectedQuantity
Tasks5
Epics1
Story Points21

Sprint Backlog

Task (Trail-*)DescriptionDeveloperStateStory Points
Trail-8UI MockupsBernardo Figueiredo, Hugo Correia, Joaquim RosaDone5
Trail-11Update DocumentationHugo CorreiaDone5
Trail-12LateX Report Repo CreationBernardo FigueiredoDone3
Trail-13Use Cases PreparationHugo CorreiaDone3
Trail-14Presentation PreparationAll teamDone5

Task Status (Completed/Not Completed)

  • Trail-8: UI Mockups
  • Trail-11: Update Documentation
  • Trail-12: LateX Report Repo Creation
  • Trail-13: Use Cases Preparation
  • Trail-14: Presentation Preparation

Sprint Review

ConcludedQuantity
Tasks5
Epics1
Story Points21

Sprint Retrospective

In this sprint, we managed to complete all the tasks that were planned. The team worked well together and managed to finish the sprint goals on time. The presentation was prepared and the documentation was updated. The LateX report repository was created and the use cases were prepared. The UI mockups were also completed.

Sprint Burnup Chart

Burndown Chart